Occupational Safety and Health Act Art. 67 · Enforcement Rule Art. 86 · MOEL Notice on the Preparation of Safety and Health Ledgers for Construction Works
Construction Safety and Health Ledgers: preparation and verification
The project owner of a construction project with a total contract value of KRW 5 billion or more must prepare and verify Safety and Health Ledgers at the planning, design and construction stages. The basic ledger is prepared by the owner and reviewed by a construction safety expert; the design ledger by the designer; and the construction ledger by the contractor, with the owner verifying implementation.
Roles by stage
- Planning: prepared by the owner, adequacy-reviewed by an expert, issued to the designer
- Design: prepared by the designer at design completion, issued to the contractor
- Construction: prepared by the contractor before commencement and submitted to the owner, who verifies implementation every three months